Clubhouse fit out is underway

The fit out of the clubhouse is underway with a large painting team applying the initial undercoat and then final coats.

The acoustic roof panels will be installed this week (20th July) along with the carpets (expected later this week). The installation of equipment (ie large format TV’s, seating, kitchen goods etc) will commence later in August . There’ll be no room for loneliness here with a fabulous range of facilities including a large dance floor for the well planned shindigs. Hoping for an official opening later in October 2020.